Venus Mill Storage (ERCOT-23INR0216) — Project Summary

Queue ID
ERCOT-23INR0216
Capacity
100.8 MW
Technology
Battery
Status
active
Location
Ellis, TX
Region
ERCOT
Developer
KCE TX 14, LLC
IA Status
Facility Study

Venus Mill Storage

ERCOT-23INR0216BetaActiveBatteryERCOTLBNL + Live

100.8 MW storage in Ellis, TX · In queue since March 2022 · Proposed COD December 2027

100.8 MW

Capacity

1

Components

Battery

4y 2m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

5y 9m

Facilities Study50%
Queue EntryMar 14, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

About

The Venus Mill Storage project is a proposed 100.8 MW battery energy storage system located in Ellis County, Texas. The project, developed by KCE TX 14, LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0216. It entered the queue on March 14, 2022, with a proposed commercial operation date of December 31, 2027. The project's interconnection status is currently in the Facility Study phase.

The Venus Mill Storage project is linked to the existing TX 14 Venus Mill Storage operating plant (EIA ID 65788). Recent news coverage indicates development activity related to the project.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Ellis

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

KCE TX 14, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

138 kV Tap #442 Rail Port - #1905 Griffith

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
HIGH
Nearest Node (Estimated)
DSWL_BES1
POI Substation
Venus Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Venus Mill Storage