Venus Mill Storage
100.8 MW storage in Ellis, TX · In queue since March 2022 · Proposed COD December 2027
100.8 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The Venus Mill Storage project is a proposed 100.8 MW battery energy storage system located in Ellis County, Texas. The project, developed by KCE TX 14, LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0216. It entered the queue on March 14, 2022, with a proposed commercial operation date of December 31, 2027. The project's interconnection status is currently in the Facility Study phase.
The Venus Mill Storage project is linked to the existing TX 14 Venus Mill Storage operating plant (EIA ID 65788). Recent news coverage indicates development activity related to the project.
Generated from interconnection queue and public data sources
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
KCE TX 14, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Tap #442 Rail Port - #1905 Griffith
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DSWL_BES1
- POI Substation
- Venus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.