Sunbelt Solar
81.5 MW generation in Kaufman, TX · In queue since March 2021 · Proposed COD December 2026
81.5 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Sunbelt Solar is a proposed 81.5 MW solar generation project located in Kaufman County, Texas. The project, developed by Rose Hill Solar LLC, is in the ERCOT interconnection queue as entry ERCOT-23INR0222, with a queue entry date of March 16, 2021. Its proposed commercial operation date is December 31, 2026, and its interconnection status is currently in the Facility Study phase.
The Sunbelt Solar project has been the subject of recent news coverage, with two articles categorized as regulatory and industry news.
Generated from interconnection queue and public data sources
State
TX
County
Kaufman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rose Hill Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 6902 Talty - 6801 Patton
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Sunbelt Solar