Garcitas Creek Solar
201.94 MW generation in Jackson, TX · In queue since October 2021 · Proposed COD December 2026
201.94 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Status
Signed Jun 2022
Queue → IA
8 months
IA → COD
4y 6m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-30
Garcitas Creek Solar is a proposed solar generation project with a total capacity of 201.94 MW. The project, located in Jackson County, Texas, is being developed by Garcitas Creek Solar LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0223, with a queue entry date of October 5, 2021, and a proposed commercial operation date of December 30, 2026.
The project's Interconnection Agreement (IA) has been executed as of June 30, 2022. The point of interconnection (POI) is the Tap 345 kV 5915 South Texas Project _x0013_ 8249 Angstrom. This proposed project is linked to the existing Garcitas Creek Solar operating plant (EIA plant ID 65973).
Generated from interconnection queue and public data sources
State
TX
County
Jackson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Garcitas Creek Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 5915 South Texas Project _x0013_ 8249 Angstrom
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- POI Substation
- Vanderbilt Substation