Morning Glory Solar
122.4 MW generation in Tom Green, TX · In queue since June 2021 · Proposed COD March 2026
122.4 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4y 9m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-31
The Morning Glory Solar project is a proposed 122.4 MW solar generation facility in Tom Green County, Texas. The project, developed by Armadillo Solar, LLC, is located within the Electric Reliability Council of Texas (ERCOT) region and entered the ERCOT interconnection queue as entry 23INR0224 on June 16, 2021. The proposed commercial operation date is March 31, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the project is the tap 345kV 7077 Amos Creek - 76009 Twin Buttes. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Armadillo Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 7077 Amos Creek - 76009 Twin Buttes
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Morning Glory Solar