Rocinante Solar
95.29 MW generation in Gonzales, TX · In queue since April 2021 · Proposed COD March 2027
95.29 MW
Capacity
1
Components
Solar
5y 1m
In Queue
—
IA Status
Signed Apr 2022
Queue → IA
1 year
IA → COD
4y 11m
Total Duration
1 year
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-16
Rocinante Solar is a proposed solar generation project located in Gonzales County, Texas, within the ERCOT region. The project, with a total capacity of 95.29 MW, is listed in the ERCOT interconnection queue as entry ERCOT-23INR0231. The queue entry date is April 22, 2021, and the proposed commercial operation date is March 16, 2027.
The project has an active interconnection agreement, which was executed on April 25, 2022.
Generated from interconnection queue and public data sources
State
TX
County
Gonzales
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Rocinante Solar