Rocinante BESS
33.17 MW storage in Gonzales, TX · Proposed COD March 2027
33.17 MW
Capacity
1
Components
Battery
—
In Queue
—
IA Status
Signed Apr 2022
IA → COD
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-03-16
The Rocinante BESS project is a proposed 33.17 MW battery storage project located in Gonzales County, Texas. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0232. The project's interconnection agreement (IA) date is April 25, 2022, and it has a proposed commercial operation date of March 16, 2027.
The development project consists solely of battery storage, with a total capacity of 33.17 MW.
Generated from interconnection queue and public data sources
State
TX
County
Gonzales
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Rocinante BESS