Earthwise Solar (ERCOT-23INR0233) — Project Summary

Queue ID
ERCOT-23INR0233
Capacity
370.5 MW
Technology
Solar
Status
active
Location
Hardeman, TX
Region
ERCOT
Developer
Quanah Solar 2
IA Status
Facility Study

Earthwise Solar

ERCOT-23INR0233BetaActiveSolarERCOTLBNL + Live

370.5 MW generation in Hardeman, TX · In queue since March 2022 · Proposed COD December 2028

370.5 MW

Capacity

1

Components

Solar

4y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

6y 9m

Facilities Study50%
Queue EntryMar 14, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

About

Earthwise Solar is a proposed 370.5 MW solar generation project located in Hardeman County, Texas. The project, developed by Quanah Solar 2, is in the ERCOT interconnection queue as entry ERCOT-23INR0233, with a queue entry date of March 14, 2022. The proposed commercial operation date is December 31, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 60504 Tesla - 61001 Jim Treece. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hardeman

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Quanah Solar 2

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 60504 Tesla - 61001 Jim Treece

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
Nearest Node (Estimated)
MISAE_GEN_RN
POI Substation
Tesla Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.