Chiltepin Solar
200 MW generation in Reeves, TX · In queue since April 2021 · Proposed COD June 2025
200 MW
Capacity
1
Components
Solar
5y 1m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
4y 2m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-30
The proposed Chiltepin Solar project is a 200 MW solar generation facility located in Reeves County, Texas. The project, developed by Chiltepin Solar-Storage, LLC, is in the ERCOT interconnection queue as entry ERCOT-23INR0234, with a queue entry date of April 22, 2021. The proposed commercial operation date is June 30, 2025, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the project is the 6673 Musquiz 138kV location. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Chiltepin Solar-Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6673 Musquiz 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Musquiz Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Chiltepin Solar