Limewood Solar
204.6 MW generation in Bell, TX · In queue since April 2021 · Proposed COD March 2026
204.6 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Status
Signed Feb 2023
Queue → IA
1y 10m
IA → COD
3y 1m
Total Duration
1y 10m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-02
Limewood Solar is a proposed 204.6 MW solar generation project located in Bell County, Texas. The developer is Limewood Bell Renewables LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-23INR0249, with an interconnection queue entry date of April 30, 2021. The proposed commercial operation date is March 2, 2026.
The project's Interconnection Agreement (IA) has been executed as of February 22, 2023. Limewood Solar is linked to the existing Limewood Bell Renewables Solar operating plant (EIA plant ID 68853). The point of interconnection is the 3420 Temple Pecan Creek 138kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Limewood Bell Renewables LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3420 Temple Pecan Creek 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LIME_SLR_UNIT1
- POI Substation
- Temple Pecan Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.