BRP Aras BESS
303.59 MW storage in Upton, TX · In queue since May 2021 · Proposed COD December 2028
303.59 MW
Capacity
1
Components
Battery
5 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The BRP Aras BESS project is a proposed 303.59 MW battery storage project located in Upton County, Texas. The developer is BRP Aras BESS LLC. It is interconnected to the ERCOT grid under queue ID ERCOT-23INR0272, with a queue entry date of May 31, 2021. The proposed commercial operation date is December 1, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 76595 North McCamey 138kV location. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Aras BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76595 North McCamey 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- North McCamey Subsation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.