BRP Nile BESS
202.34 MW storage in Webb, TX · In queue since May 2021 · Proposed COD December 2027
202.34 MW
Capacity
1
Components
Battery
5 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The BRP Nile BESS project is a proposed 202.34 MW battery storage project located in Webb County, Texas. The developer is BRP Nile BESS LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0275, with a queue entry date of May 31, 2021.
The project's proposed commercial operation date is December 1, 2027. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 80220 Cenizo 345kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Nile BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80220 Cenizo 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cenizo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.