BRP Trivor BESS (ERCOT-23INR0279) — Project Summary

Queue ID
ERCOT-23INR0279
Capacity
202.34 MW
Technology
Battery
Status
active
Location
Andrews, TX
Region
ERCOT
Developer
BRP Trivor BESS LLC
IA Status
Facility Study

BRP Trivor BESS

ERCOT-23INR0279BetaActiveBatteryERCOTLBNL + Live

202.34 MW storage in Andrews, TX · In queue since June 2021 · Proposed COD March 2028

202.34 MW

Capacity

1

Components

Battery

4y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

6y 9m

Facilities Study50%
Queue EntryJun 3, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-01

About

The BRP Trivor BESS project is a proposed 202.34 MW battery storage project located in Andrews County, Texas. The developer is BRP Trivor BESS LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0279, with a queue entry date of June 3, 2021. The proposed commercial operation date is March 1, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 1272 Fullerton 138kV substation. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Andrews

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Trivor BESS LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

1272 Fullerton 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Exxon Fullerton Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.