Dry Creek Solar I
201.06 MW generation in Rusk, TX · In queue since August 2021 · Proposed COD January 2026
201.06 MW
Capacity
1
Components
Solar
4y 9m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
2y 3m
IA → COD
2y 2m
Total Duration
2y 3m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-01-31
Dry Creek Solar I is a proposed 201.06 MW solar generation project located in Rusk County, Texas. The developer is OAK HILL SOLAR LLC. The project is in the ERCOT interconnection queue as entry ERCOT-23INR0286, with a queue entry date of August 18, 2021, and a proposed commercial operation date of January 31, 2026.
The project's Interconnection Agreement (IA) was executed on November 2, 2023. Dry Creek Solar I has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Rusk
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
OAK HILL SOLAR LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 3100 Martin Lake - 3105 Elkton (Dorsett 345kV Switching Station)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MLSES_UNIT1
- POI Substation
- Martin Lake Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Dry Creek Solar I