Dry Creek Solar I (ERCOT-23INR0286) — Project Summary

Queue ID
ERCOT-23INR0286
Capacity
201.06 MW
Technology
Solar
Status
active
Location
Rusk, TX
Region
ERCOT
Developer
OAK HILL SOLAR LLC
IA Status
IA Executed

Dry Creek Solar I

ERCOT-23INR0286BetaActiveSolarERCOTLBNL + Live

201.06 MW generation in Rusk, TX · In queue since August 2021 · Proposed COD January 2026

201.06 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Executed

IA Status

Signed Nov 2023

Interconnection

Queue → IA

2y 3m

IA → COD

2y 2m

Total Duration

2y 3m

Schedule

3 months past proposed COD

Construction75%
Queue EntryAug 18, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 2, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-01-31

About

Dry Creek Solar I is a proposed 201.06 MW solar generation project located in Rusk County, Texas. The developer is OAK HILL SOLAR LLC. The project is in the ERCOT interconnection queue as entry ERCOT-23INR0286, with a queue entry date of August 18, 2021, and a proposed commercial operation date of January 31, 2026.

The project's Interconnection Agreement (IA) was executed on November 2, 2023. Dry Creek Solar I has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Rusk

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

OAK HILL SOLAR LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 3100 Martin Lake - 3105 Elkton (Dorsett 345kV Switching Station)

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
MLSES_UNIT1
POI Substation
Martin Lake Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.