Avila BESS
164.28 MW storage in Pecos, TX · In queue since May 2021 · Proposed COD May 2025
164.28 MW
Capacity
1
Components
Battery
5 years
In Queue
IA Executed
IA Status
Signed Feb 2023
Queue → IA
1y 9m
IA → COD
2y 3m
Total Duration
1y 9m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-05-01
The Avila BESS project is a proposed 164.28 MW battery storage project located in Pecos County, Texas. The developer is BRP Avila BESS LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-23INR0287, with a queue entry date of May 31, 2021, and a proposed commercial operation date of May 1, 2025.
The project's Interconnection Agreement (IA) has been executed as of February 6, 2023. The point of interconnection is the 38340 TN Airport 138kV substation. The Avila BESS project is linked to the existing Avila operating plant (EIA plant ID 65860).
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Avila BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38340 TN Airport 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- AVIL_ESS_RN
- POI Substation
- Airport Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.