Anole BESS
247.1 MW storage in Dallas, TX · In queue since July 2021 · Proposed COD May 2025
247.1 MW
Capacity
1
Components
Battery
4y 10m
In Queue
IA Executed
IA Status
Signed Apr 2023
Queue → IA
1y 9m
IA → COD
2y 1m
Total Duration
1y 9m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-05-30
Anole BESS is a proposed battery storage project located in Dallas County, Texas, with a total capacity of 247.1 MW. Developed by Anole Energy Storage, LLC, the project consists entirely of battery storage. It is listed in the ERCOT interconnection queue as entry ERCOT-23INR0299, with a queue entry date of July 1, 2021, and a proposed commercial operation date of May 30, 2025.
The project's interconnection agreement (IA) was executed on April 26, 2023. The point of interconnection (POI) is the 2432 Tri-Corner 345kV. The project is linked to the existing Anole Energy Storage operating plant (EIA plant ID 67740). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dallas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anole Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
2432 Tri-Corner 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TRICRN1_5
- POI Substation
- Tri-Corner Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.