Dunkel BESS
225 MW storage in Lubbock, TX · In queue since June 2022 · Proposed COD November 2027
225 MW
Capacity
1
Components
Battery
3y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-02
The Dunkel BESS project is a proposed 225 MW battery storage project located in Lubbock County, Texas. Developed by Momentum Energy Storage Partners, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0310, with a queue entry date of June 27, 2022.
The proposed commercial operation date for Dunkel BESS is November 2, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 59156 Yellow House Canyon 115kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Lubbock
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Momentum Energy Storage Partners
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59156 Yellow House Canyon 115kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.