Hofbrau BESS
180.72 MW storage in Tom Green, TX · In queue since September 2021 · Proposed COD July 2028
180.72 MW
Capacity
1
Components
Battery
4y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The Hofbrau BESS project is a proposed 180.72 MW battery storage project located in Tom Green County, Texas. Developed by Momentum Hofbrau LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0312, with a queue entry date of September 22, 2021.
The proposed commercial operation date for the Hofbrau BESS project is July 1, 2028. The project's interconnection status is currently in the Facility Study phase. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Momentum Hofbrau LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6442 Redcreek 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hofbrau BESS