Orange Grove BESS
61.39 MW storage in Jim Wells, TX · In queue since July 2021 · Proposed COD April 2027
61.39 MW
Capacity
1
Components
Battery
4y 10m
In Queue
IA Executed
IA Status
Signed Nov 2022
Queue → IA
1y 4m
IA → COD
4y 5m
Total Duration
1y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-04-30
Orange Grove BESS is a proposed 61.39 MW battery storage project located in Jim Wells County, Texas. The project, developed by Talitha Energy Project, LLC, consists of a single 61.39 MW battery component. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0331, with a queue entry date of July 15, 2021.
The project's proposed commercial operation date is April 30, 2027. An Interconnection Agreement (IA) for the project has been executed as of November 30, 2022. The point of interconnection is the 5660 Orange Grove Switching Station 138 kV.
Generated from interconnection queue and public data sources
State
TX
County
Jim Wells
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Talitha Energy Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5660 Orange Grove Switching Station 138 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- OGS_SLR_RN
- POI Substation
- Orange Grove Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Orange Grove BESS