Backwater Solar
80 MW generation in Cooke, TX · In queue since August 2021 · Proposed COD May 2027
80 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-06
Backwater Solar is a proposed 80 MW solar generation project located in Cooke County, Texas. The project, developed by Backwater Solar LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0332. It entered the interconnection queue on August 24, 2021, with a proposed commercial operation date of May 6, 2027. The project's interconnection status is currently in the Facility Study phase.
The Backwater Solar project has been the subject of recent news coverage, with 17 articles appearing in categories such as industry, deals, development, and grid.
Generated from interconnection queue and public data sources
State
TX
County
Cooke
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Backwater Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV line from Spring (#684) - Leo(#685)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Backwater Solar