BRP Bachman BESS
411.04 MW storage in Wharton, TX · In queue since October 2021 · Proposed COD December 2027
411.04 MW
Capacity
1
Components
Battery
4y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The proposed BRP Bachman BESS project is a 411.04 MW battery storage project located in Wharton County, Texas. Developed by BRP Bachman BESS LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0335, with a queue entry date of October 5, 2021.
The project's proposed commercial operation date is December 1, 2027. Its interconnection agreement status is currently in the Facility Study phase. The Point of Interconnection (POI) is the 44040 BAILEY 345kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Bachman BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44040 BAILEY 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Eldorado Shell Bailey Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.