Hermes Solar
100.36 MW generation in Bell, TX · In queue since September 2021 · Proposed COD April 2026
100.36 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
2y 2m
IA → COD
2y 5m
Total Duration
2y 2m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-04-17
The Hermes Solar project is a proposed 100.36 MW solar generation facility in Bell County, Texas. The project, developed by Bell Solar 1 LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0344. It entered the queue on September 21, 2021, and has a proposed commercial operation date of April 17, 2026. The interconnection agreement for the project was executed on November 8, 2023.
The proposed project is linked to the existing Hermes Solar PV operating plant (EIA plant ID 68851). Hermes Solar has been the subject of recent news coverage, including reports in industry and deals publications.
Generated from interconnection queue and public data sources
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bell Solar 1 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- STLHS_SL_RN
- POI Substation
- Rogers Substation