Tokio Solar (ERCOT-23INR0349) — Project Summary

Queue ID
ERCOT-23INR0349
Capacity
170.45 MW
Technology
Solar
Status
active
Location
Mclennan, TX
Region
ERCOT
Developer
Gransolar Texas Eight, LLC
IA Status
IA Executed

Tokio Solar

ERCOT-23INR0349BetaActiveSolarERCOTLBNL + Live

170.45 MW generation in Mclennan, TX · In queue since August 2021 · Proposed COD August 2027

170.45 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Executed

IA Status

Signed Nov 2023

Interconnection

Queue → IA

2y 3m

IA → COD

3y 9m

Total Duration

2y 3m

Construction75%
Queue EntryAug 12, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 6, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-08-25

About

Tokio Solar is a proposed solar generation project located in McLennan County, Texas, with a total capacity of 170.45 MW. The project, developed by Gransolar Texas Eight, LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0349. The project entered the queue on August 12, 2021, and has a proposed commercial operation date of August 25, 2027. The Interconnection Agreement (IA) was executed on November 6, 2023.

The proposed project is linked to the existing Tokio Solar operating plant (EIA plant ID 66397). Recent news coverage indicates industry interest in the development.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Mclennan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Gransolar Texas Eight, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 3592 Waco Atco - 170 Cotton Belt

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
POI Substation
Cotton Belt Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.