Bordertown BESS
100 MW storage in Starr, TX · In queue since September 2021 · Proposed COD June 2027
100 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Status
Signed Oct 2022
Queue → IA
1y 1m
IA → COD
4y 8m
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-06-15
The Bordertown BESS project is a proposed 100 MW battery storage project located in Starr County, Texas. Developed by Bordertown BESS LLC, the project entered the ERCOT interconnection queue as ERCOT-23INR0354 on September 1, 2021. The project's proposed commercial operation date is June 15, 2027.
The Bordertown BESS project has an Interconnection Agreement (IA) executed on October 12, 2022. The point of interconnection is the 8796 Roma 138kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Starr
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bordertown BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8796 Roma 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- STAR_SLR_RN
- POI Substation
- Roma Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bordertown BESS