Cross Trails Storage
58.29 MW storage in Scurry, TX · In queue since November 2021 · Proposed COD May 2025
58.29 MW
Capacity
1
Components
Battery
4y 6m
In Queue
IA Executed
IA Status
Signed Jul 2024
Queue → IA
2y 8m
IA → COD
10 months
Total Duration
2y 8m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-05-26
Cross Trails Storage is a proposed 58.29 MW battery storage project located in Scurry County, Texas. The project, developed by Cross Trails Energy Storage Project, LLC, consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0372, with a queue entry date of November 3, 2021, and a proposed commercial operation date of May 26, 2025.
The project's Interconnection Agreement (IA) has been executed as of July 18, 2024. The point of interconnection (POI) is the 60090 WKN Breaker 69kV. Cross Trails Storage has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cross Trails Energy Storage Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60090 WKN Breaker 69kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26