Fronton Solar 1
132.7 MW generation in Starr, TX · In queue since October 2021 · Proposed COD December 2026
132.7 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-14
Fronton Solar 1 is a proposed solar generation project with a total capacity of 132.7 MW. The project is located in Starr County, Texas, and is being developed by Meshek USA Inc. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0373, with a queue entry date of October 5, 2021. The proposed commercial operation date is December 14, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project will interconnect at the 8796 Roma Substation 138kV. Recent news coverage has discussed this project.
Generated from interconnection queue and public data sources
State
TX
County
Starr
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Meshek USA Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8796 Roma Substation 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- STAR_SLR_RN
- POI Substation
- Roma Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Fronton Solar 1