Grand Acres
153.03 MW generation in Cameron, TX · In queue since October 2021 · Proposed COD February 2027
153.03 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-23
The Grand Acres project is a proposed 153.03 MW solar generation facility in Cameron County, Texas. The project, developed by Meshek USA Inc., is located within the ERCOT region and interconnected to the 8359 South Santa Rosa 138 kV point of interconnection. It entered the ERCOT interconnection queue as project ERCOT-23INR0374 on October 7, 2021, and has a proposed commercial operation date of February 23, 2027. Its interconnection status is currently in the Facility Study phase.
The Grand Acres project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Meshek USA Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8359 South Santa Rosa 138 kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MYRY_BES2_RN
- POI Substation
- South Santa Rosa Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.