Bexar ESS
102.6 MW storage in Bexar, TX · In queue since September 2021 · Proposed COD February 2026
102.6 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Status
Signed Jul 2023
Queue → IA
1y 10m
IA → COD
2y 7m
Total Duration
1y 10m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-02-10
The Bexar ESS project is a proposed 102.6 MW battery storage project located in Bexar County, Texas. Developed by Bexar ESS LLC, the project consists entirely of battery storage. It is interconnected within the ERCOT region under queue ID ERCOT-23INR0381, with an interconnection queue entry date of September 21, 2021. The proposed commercial operation date is February 10, 2026, and the Interconnection Agreement was executed on July 31, 2023.
The project is linked to the existing Bexar ESS operating plant (EIA plant ID 66400). The Bexar ESS project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bexar ESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5007 Alamo One 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- RN_OCI_ALAMO
- POI Substation
- OCI Alamo 1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.