Camp Creek Solar SLF
165.6 MW generation in Robertson, TX · In queue since December 2021 · Proposed COD September 2028
165.6 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Status
Signed Jul 2023
Queue → IA
1y 7m
IA → COD
5y 2m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-09-15
The Camp Creek Solar SLF project is a proposed 165.6 MW solar generation project located in Robertson County, Texas. Developed by White Rock Solar, LLC, the project is currently in the ERCOT interconnection queue as entry ERCOT-23INR0385, with a queue entry date of December 24, 2021. The proposed commercial operation date is September 15, 2028. The project's Interconnection Agreement (IA) has been executed as of July 15, 2023.
The Camp Creek Solar SLF project has been featured in recent news coverage. The point of interconnection is at the TAP 345 KV 3400 TWIN OAK SWITCH - 46020 LIMESTONE PLANT CIRCUIT 1.
Generated from interconnection queue and public data sources
State
TX
County
Robertson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
White Rock Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345 KV 3400 TWIN OAK SWITCH - 46020 LIMESTONE PLANT CIRCUIT 1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26