Pioneer DJ Wind
140.32 MW generation in Midland, TX · In queue since October 2021 · Proposed COD January 2025
140.32 MW
Capacity
1
Components
Wind
4y 7m
In Queue
IA Executed
IA Status
Signed Apr 2023
Queue → IA
1y 6m
IA → COD
1y 9m
Total Duration
1y 6m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2025-01-31
The Pioneer DJ Wind project is a proposed 140.32 MW wind generation facility in Midland County, Texas. Developed by Pioneer Hutt Wind Energy LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-23INR0387. The project entered the interconnection queue on October 11, 2021, with a proposed commercial operation date of January 31, 2025.
The project's Interconnection Agreement (IA) was executed on April 4, 2023. The point of interconnection is the 138 kV Driver station (Bus #: 23863). The Pioneer DJ Wind project is linked to the existing Pioneer Hutt Wind Energy operating plant (EIA ID 66531).
Generated from interconnection queue and public data sources
State
TX
County
Midland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pioneer Hutt Wind Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Driver station (Bus #: 23863)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PIONR_DJ_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pioneer DJ Wind