Angelo Storage
102.97 MW storage in Tom Green, TX · In queue since November 2021 · Proposed COD November 2024
102.97 MW
Capacity
1
Components
Battery
4y 6m
In Queue
IA Executed
IA Status
Signed Dec 2021
Queue → IA
1 month
IA → COD
2y 11m
Total Duration
1 month
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2024-11-15
Angelo Storage is a proposed 102.97 MW battery storage project located in Tom Green County, Texas. The project, developed by Angelo Storage, LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0418. It entered the interconnection queue on November 22, 2021, with a proposed commercial operation date of November 15, 2024. The Interconnection Agreement (IA) for the project has been executed as of December 3, 2021.
The proposed project is linked to the existing Angelo Storage operating plant (EIA plant ID 68146). Recent news coverage indicates activity related to the project, specifically in the area of deals.
Generated from interconnection queue and public data sources
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Angelo Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76009 Twin Buttes 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ANG_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Angelo Storage