Smokey Willie Solar SLF
200.92 MW generation in Anderson, TX · In queue since January 2022 · Proposed COD September 2028
200.92 MW
Capacity
1
Components
Solar
4y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
The Smokey Willie Solar SLF project is a proposed 200.92 MW solar generation facility in Anderson County, Texas. The project, being developed by Neches Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0439, with a queue entry date of January 6, 2022. The proposed commercial operation date is September 30, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 3325 Blackburn Switch _x0013_ 3272 Palestine. The project consists of 200.92 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
TX
County
Anderson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Neches Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3325 Blackburn Switch _x0013_ 3272 Palestine
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.