Bug Tussle Wind Project
396.8 MW generation in Lamar, TX · In queue since January 2022 · Proposed COD September 2028
396.8 MW
Capacity
1
Components
Wind
4y 4m
In Queue
IA Executed
IA Status
Signed Jul 2024
Queue → IA
2y 6m
IA → COD
4y 2m
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2028-09-18
The Bug Tussle Wind Project is a proposed 396.8 MW wind generation project located in Lamar County, Texas. The developer is Bug Tussle Wind, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-23INR0441, with a queue entry date of January 13, 2022, and a proposed commercial operation date of September 18, 2028.
The project's interconnection agreement has been executed as of July 10, 2024. The point of interconnection is Tap 1729 Valley South and 1692 Paris. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bug Tussle Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 1729 Valley South and 1692 Paris
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.