Bronze Quinta Storage
103.51 MW storage in Hidalgo, TX · In queue since January 2022 · Proposed COD January 2028
103.51 MW
Capacity
1
Components
Battery
4y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
The Bronze Quinta Storage project is a proposed 103.51 MW battery storage project located in Hidalgo County, Texas. The developer is KCE TX 28, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0456, with a queue entry date of January 13, 2022. The proposed commercial operation date is January 1, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the S_MCALLN 8371 (S. McAllen 138kV Substation). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Hidalgo
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
KCE TX 28, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
S_MCALLN 8371 (S. McAllen 138kV Substation)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bronze Quinta Storage