Ophelia Solar
110.5 MW generation in Ector, TX · In queue since September 2022 · Proposed COD September 2028
110.5 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-19
Ophelia Solar is a proposed 110.5 MW solar generation project located in Ector County, Texas. The development project, sponsored by Ophelia Solar, entered the ERCOT interconnection queue as entry ERCOT-23INR0471 on September 2, 2022. Its proposed commercial operation date is September 19, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is tapping the 138 kV line from Moss Switch (Bus# 1019) to Shin Oak POD (Bus# 11128), with a 110 MW PUN load at the high side of the MPT. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ophelia Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tapping the 138 kV Line from Moss Switch (Bus# 1019) to Shin Oak POD (Bus# 11128). The project has a 110 MW PUN load at the high side of the MPT (refer to the substation SLD).
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Ophelia Solar