Sepanta Solar
217.26 MW generation in Nolan, TX · In queue since October 2022 · Proposed COD September 2029
217.26 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-18
The Sepanta Solar project is a proposed solar generation facility with a total capacity of 217.26 MW. The project is located in Nolan County, Texas, and is being developed by BREG - Belgian Renewable Energy Group. It is currently in the ERCOT interconnection queue as project ERCOT-23INR0473, with an interconnection queue entry date of October 18, 2022. The proposed commercial operation date is September 18, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection (POI) is at the 1339 ESKOTA_9 138kV substation, adjacent to the Oncor Sweetwater Eskota Switch #1339. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Nolan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BREG - Belgian Renewable Energy Group
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1339 ESKOTA_9 138kV (PSS/E BUS #1339, Station Name: ESKOTA_8, kV: 138 kV) Property is adjacent (West) to the Oncor Sweetwater Eskota Switch #1339. POI would simply be on the other side of the fence of the switch.
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Sepanta Solar