AP Greenport
100.45 MW storage in Travis, TX · In queue since June 2022 · Proposed COD November 2027
100.45 MW
Capacity
1
Components
Battery
3y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-19
The AP Greenport project is a proposed 100.45 MW battery storage project located in Travis County, Texas. The developer is listed as AP Greenport. This project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0474, with a queue entry date of June 10, 2022. The proposed commercial operation date is November 19, 2027. The project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection is the Austrop - Lost Pines 345 kV transmission line (Bus #7040 - 9041). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Travis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
AP Greenport
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Austrop _x0013_ Lost Pines 345 kV transmission line (Bus #7040 _x0013_ 9041)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.