XE Rhoda Storage (ERCOT-23INR0478) — Project Summary

Queue ID
ERCOT-23INR0478
Capacity
141.23 MW
Technology
Battery
Status
active
Location
Milam, TX
Region
ERCOT
Developer
Milam Energy, LLC
IA Status
Facility Study

XE Rhoda Storage

ERCOT-23INR0478BetaActiveBatteryERCOTLBNL + Live

141.23 MW storage in Milam, TX · In queue since April 2022 · Proposed COD April 2028

141.23 MW

Capacity

1

Components

Battery

4y 1m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

6 years

Facilities Study50%
Queue EntryApr 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-07

About

The proposed XE Rhoda Storage project is a 141.23 MW battery energy storage system located in Milam County, Texas. Developed by Milam Energy, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0478, with a queue entry date of April 18, 2022. The proposed commercial operation date is April 7, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection for the XE Rhoda Storage project is Tap 138kV 32 Robertson - 64 Milano. The project consists solely of battery storage, with a total capacity of 141.23 MW. The project has appeared in recent news coverage regarding energy storage development in Texas.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Milam

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Milam Energy, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 32 Robertson - 64 Milano

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Robertson Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about XE Rhoda Storage