XE Rhoda Storage
141.23 MW storage in Milam, TX · In queue since April 2022 · Proposed COD April 2028
141.23 MW
Capacity
1
Components
Battery
4y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-07
The proposed XE Rhoda Storage project is a 141.23 MW battery energy storage system located in Milam County, Texas. Developed by Milam Energy, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0478, with a queue entry date of April 18, 2022. The proposed commercial operation date is April 7, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the XE Rhoda Storage project is Tap 138kV 32 Robertson - 64 Milano. The project consists solely of battery storage, with a total capacity of 141.23 MW. The project has appeared in recent news coverage regarding energy storage development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Milam Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 32 Robertson - 64 Milano
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Robertson Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about XE Rhoda Storage