Taormina Storage
231.86 MW storage in Bexar, TX · In queue since April 2022 · Proposed COD May 2029
231.86 MW
Capacity
1
Components
Battery
4y 1m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-26
The Taormina Storage project is a proposed 231.86 MW battery energy storage system in Bexar County, Texas. Developed by Taormina Storage Project LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0479, with a queue entry date of April 18, 2022. The proposed commercial operation date is May 26, 2029.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV VH Braunig (5025) to Valley Road 138kV (5465). The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Taormina Storage Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV VH Braunig (5025) to Valley Road 138kV (5465)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.