Hacienda Storage (ERCOT-23INR0485) — Project Summary

Queue ID
ERCOT-23INR0485
Capacity
201.9 MW
Technology
Battery
Status
active
Location
Galveston, TX
Region
ERCOT
Developer
Galveston Energy Storage LLC
IA Status
Facility Study

Hacienda Storage

ERCOT-23INR0485BetaActiveBatteryERCOTLBNL + Live

201.9 MW storage in Galveston, TX · In queue since May 2022 · Proposed COD December 2027

201.9 MW

Capacity

1

Components

Battery

4 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

5y 7m

Facilities Study50%
Queue EntryMay 10, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

About

The Hacienda Storage project is a proposed 201.9 MW battery energy storage system located in Galveston County, Texas. The project, being developed by Galveston Energy Storage LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0485, with a queue entry date of May 10, 2022.

The proposed commercial operation date for Hacienda Storage is December 1, 2027. The project's interconnection status is currently in the Facility Study phase, and it intends to connect to the 38745 Attwater 138kV point of interconnection. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Galveston

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Galveston Energy Storage LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

38745 Attwater 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.