Lamar Unit 1 Repower
66 MW generation in Lamar, TX · In queue since June 2022 · Proposed COD December 2027
66 MW
Capacity
1
Components
Gas
3y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-18
The Lamar Unit 1 Repower is a proposed 66 MW gas-fired generation project located in Lamar County, Texas. The project is being developed by La Frontera Holdings, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0486, with a queue entry date of June 2, 2022, and a proposed commercial operation date of December 18, 2027. The project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of a single 66 MW gas-fired generator. The point of interconnection is the 1692 Paris Switch Station at 345kV. The Lamar Unit 1 Repower project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
La Frontera Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1692 Paris Switch Station 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CAMWIND_RN
- POI Substation
- Paredes Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.