Brightside Solar Alt POI
50 MW generation in Live Oak, TX · In queue since May 2022 · Proposed COD August 2026
50 MW
Capacity
1
Components
Solar
4 years
In Queue
IA Executed
IA Status
Signed Jun 2020
IA → COD
6y 2m
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-08-14
Brightside Solar Alt POI is a proposed 50 MW solar generation project located in Live Oak County, Texas. The project, developed by Brightside Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-23INR0487, with a queue entry date of May 16, 2022. The proposed commercial operation date is August 14, 2026.
The project's interconnection agreement has been executed as of June 11, 2020. The point of interconnection is the 8156 Charter Substation 138kV. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Live Oak
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Brightside Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8156 Charter Substation 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.