Laureles BESS
9.8 MW storage in Cameron, TX · In queue since October 2022 · Proposed COD June 2025
9.8 MW
Capacity
1
Components
Battery
3y 7m
In Queue
IA Executed
IA Status
Signed Feb 2023
Queue → IA
4 months
IA → COD
2y 4m
Total Duration
4 months
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-06-21
The Laureles BESS project is a proposed 9.8 MW battery storage project located in Cameron County, Texas. The developer is Regis Laureles LLC. It is interconnected within the ERCOT region under queue ID ERCOT-23INR0499, with a queue entry date of October 21, 2022, and a proposed commercial operation date of June 21, 2025.
The project's Interconnection Agreement (IA) has been executed as of February 16, 2023. The Point of Interconnection (POI) is at the LAURELES station, load transformer LD01, bus number 5756, at 138kV.
Generated from interconnection queue and public data sources
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Regis Laureles LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Station Name (TDSP Station Code) LAURELES; Load/Load Transformer Name LD01; PTI BUS number 5756; Voltage in kV (Transmission Level) 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.