Adelite Storage
231.88 MW storage in Milam, TX · In queue since June 2022 · Proposed COD June 2027
231.88 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Status
Signed Aug 2024
Queue → IA
2y 2m
IA → COD
2y 10m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-06-28
Adelite Storage is a proposed 231.88 MW battery storage project located in Milam County, Texas. The developer is Adelite Storage Project LLC. This project is interconnected within the ERCOT region under queue ID ERCOT-23INR0502, with an interconnection queue entry date of June 27, 2022, and a proposed commercial operation date of June 28, 2027. The Interconnection Agreement (IA) for this project was executed on August 27, 2024.
The project is linked to the existing Adelite Storage Project LLC operating plant (EIA ID 69004). The point of interconnection (POI) is at Tap 138kV Thorndale North (bus #3659) _x0013_ Rookie Switch (bus #3701). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Adelite Storage Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Thorndale North (bus #3659) _x0013_ Rookie Switch (bus #3701)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- POI Substation
- Thorndale North Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Adelite Storage