Torrecillas BESS
9.9 MW storage in Webb, TX · Proposed COD May 2025
9.9 MW
Capacity
1
Components
Battery
—
In Queue
IA Executed
IA Status
Signed Jan 2015
IA → COD
10y 4m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-05-19
The Torrecillas BESS project is a proposed 9.9 MW battery storage project located in Webb County, Texas. Developed by Torrecillas Interconnect, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-23INR0529. The project has an Interconnection Agreement (IA) executed as of January 30, 2015, and a proposed commercial operation date of May 19, 2025.
The project consists solely of battery storage, with a total capacity of 9.9 MW. The point of interconnection is the 161257 Torrecillas 345kV station (Station code: TORR). The project is currently listed as active in the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Torrecillas Interconnect, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
161257 Torrecillas 345kV Station code: TORR
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Torrecillas BESS