Roadrunner Crossing BESS SLF
40 MW storage in Eastland, TX · In queue since November 2022 · Proposed COD February 2026
40 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 3m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-13
The Roadrunner Crossing BESS SLF project is a proposed 40 MW battery storage project located in Eastland County, Texas. Developed by Roadrunner Crossing BESS, the project entered the ERCOT interconnection queue as entry ERCOT-23INR0538 on November 15, 2022. The current proposed commercial operation date is February 13, 2026. The project's interconnection status is currently in the Facility Study phase.
The Roadrunner Crossing BESS SLF project has appeared in recent news coverage regarding energy storage development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Eastland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Roadrunner Crossing BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68051 Reata 354kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.