Goodnight Wind II
259.2 MW generation in Armstrong, TX · In queue since April 2023 · Proposed COD June 2027
259.2 MW
Capacity
1
Components
Wind
3y 1m
In Queue
IA Executed
IA Status
Signed Aug 2019
IA → COD
7y 10m
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-06-14
Goodnight Wind II is a proposed wind generation project located in Armstrong County, Texas, with a total capacity of 259.2 MW. The developer is FGE Goodnight II, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-23INR0637, with a queue entry date of April 19, 2023, and a proposed commercial operation date of June 14, 2027. The Interconnection Agreement (IA) has been executed as of August 18, 2019.
This development is linked to the existing Goodnight operating plant (EIA ID 59246). The point of interconnection (POI) is at tap 345kV 23900 Alibates - 23914 Tule Canyon CKT2. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Armstrong
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
FGE Goodnight II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 23900 Alibates - 23914 Tule Canyon CKT2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ERCOT Panhandle
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.