Nockenut Springs Solar 2
203.26 MW generation in Guadalupe, TX · In queue since September 2020 · Proposed COD June 2029
203.26 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-05
Nockenut Springs Solar 2 is a proposed solar generation project located in Guadalupe County, Texas, within the ERCOT region. The project, developed by Pecan Springs Energy, LLC, has a total capacity of 203.26 MW. It consists entirely of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0007, with a queue entry date of September 25, 2020. The proposed commercial operation date is June 5, 2029. Its interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
TX
County
Guadalupe
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pecan Springs Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 5133 Elm Creek - 5915 STP ckt 1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Elm Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Nockenut Springs Solar 2