PP Jaguar Solar
300 MW generation in Mclennan, TX · In queue since March 2021 · Proposed COD December 2027
300 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Sep 2022
Queue → IA
1y 6m
IA → COD
5y 3m
Total Duration
1y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-11
PP Jaguar Solar is a proposed 300 MW solar generation project located in McLennan County, Texas. The project, developed by PP Jaguar Solar LLC, is interconnected within the ERCOT region under queue ID ERCOT-24INR0038. It entered the interconnection queue on March 18, 2021, and has a proposed commercial operation date of December 11, 2027. The project's Interconnection Agreement (IA) was executed on September 12, 2022.
The interconnection point of contact is Tap 345kV 13405 Tradinghouse SES - 68090 Sam Switch. The project has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Mclennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
PP Jaguar Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 13405 Tradinghouse SES - 68090 Sam Switch
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- JAG_SLR_RN
- POI Substation
- Tradinghouse Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.