PP Jaguar BESS
314.25 MW storage in Mclennan, TX · In queue since March 2021 · Proposed COD June 2025
314.25 MW
Capacity
1
Components
Battery
5y 2m
In Queue
IA Executed
IA Status
Signed Sep 2022
Queue → IA
1y 6m
IA → COD
2y 9m
Total Duration
1y 6m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-06-30
PP Jaguar BESS is a proposed 314.25 MW battery storage project located in McLennan County, Texas. The project, developed by PP Jaguar BESS LLC, is interconnected within the ERCOT region. It consists entirely of battery storage.
The project entered the ERCOT interconnection queue as ERCOT-24INR0039 on March 18, 2021, with a proposed commercial operation date of June 30, 2025. An Interconnection Agreement (IA) for the project was executed on September 12, 2022. The point of interconnection is Tap 345kV 13405 Tradinghouse SES - 68090 Sam Switch.
Generated from interconnection queue and public data sources
State
TX
County
Mclennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
PP Jaguar BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 13405 Tradinghouse SES - 68090 Sam Switch
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- JAG_SLR_RN
- POI Substation
- Tradinghouse Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.