Rosebud Solar SLF
130 MW generation in Falls, TX · In queue since April 2021 · Proposed COD January 2028
130 MW
Capacity
1
Components
Solar
5y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-15
The Rosebud Solar SLF project is a proposed 130 MW solar generation facility in Falls County, Texas. The project, developed by Rosebud Solar, LLC, is located within the Electric Reliability Council of Texas (ERCOT) region. It consists of 130 MW of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0040, with a queue entry date of April 13, 2021. The proposed commercial operation date is January 15, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
TX
County
Falls
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rosebud Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 69kV 67 BAGGINS - 69 BARCLAY
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.